Panel Sizing Methodology: Power, Wire, Protection

Load, wire, protection, then heat.

Methodology

Size as a system: total the loads with demand, choose wire for ampacity and voltage drop, then select protection per NEC 240 and 430. Check heat last.

Formulas

Three-phase power

\[P = \sqrt{3} \times V \times I \times PF\]

Real power from line voltage, line current, and displacement power factor.

Voltage drop (1-phase)

\[V_d = \frac{2 K I L}{cmil}\]

K is 12.9 for copper and 21.2 for aluminum; L is one-way length.

Worked example

Checking a motor feeder

Inputs: Three 460V motors: 12.2A, 8.0A, 4.5A; 6A other continuous load.

Calculation: Feeder = 1.25 x 12.2 + 8.0 + 4.5 + 1.25 x 6 = 35.25A, about 29.3 kVA at 480V.

Lesson:

Frequently asked questions

Which comes first, wire or breaker?

Load first, then wire for ampacity and drop, then protection. Protection guards the wire; it never substitutes for ampacity.

Do these tools replace an engineered review?

No. They screen sizes against common NEC rules. Derating, short-circuit ratings, and local amendments need site review; the AHJ governs.

Sources and further verification

  1. NFPA 70, National Electrical Code National Fire Protection Association
  2. Electrical Safety in the Workplace NFPA

Next step

Run the multi-motor summary

Open calculator

Keep reading

Related articles.